Date

Description

FCRC-No

Monday, 6 December 2021

Application  Stage - Starts

Monday, 6 December 2021

The Assessment Manager (FCRC) received development application DA21 which included in its ‘common material’ a planning report (PR21) from the Appellant's consultant planner. SARA as referral (concurrence) agency was provided with a copy of DA21

1

Wednesday, 8 December 2021

FCRC Confirms - Properly Made

Thursday, 9 December 2021

FCRC Determines Application Type

Monday, 13 December 2021

FCRC Generate and sends Confirmation Notice - Part 1 Application Period End:

2

Monday, 13 December 2021

Application  Stage - Ends

Monday, 28 February 2022

Refferal & Information Request Stage  - Starts

Tuesday, 14 December 2021

FCRC -Part 2 Referral: & Part 3 Information Request- Start:  FCRC and the Appellant agreed to extend the period of time for FCRC to make an information request to 14 January 2022.

3

Monday, 20 December 2021

SARA issued their Confirmation Notice

7

Friday, 7 January 2022

SARA issued an Information Request. (SIR)

4

Thursday, 13 January 2022

 FCRC issued an Information Request. (CIR)

5 and 6

Monday, 7 March 2022

Applicant Requests pause on Information Response

Sunday, 17 April 2022

Applicant Requests pause on Information Response

Thursday, 5 May 2022

SARA Response: Extends response period to 15/6/2022

8

Tuesday, 31 May 2022

Applicant Requests extension on Information Response to 17/7/2022

9

Wednesday, 1 June 2022

FCRC Extension Agreement to 15/8/2022

10

Wednesday, 27 July 2022

Applicant Seek extension to Information Response by 40 Days

11

Thursday, 18 August 2022

Email From Tony Mc Vey- Confirming negotiation with HQP Option outcome

17

Wednesday, 14 September 2022

Applicant Seek extension to Information Response by 40 Days

12

Wednesday, 9 November 2022

Applicant Requests extension on Information Response to 31/1/2023

13

Tuesday, 15 November 2022

Information Response After App Stop Current Prd

Monday, 21 November 2022

SARA Response: Extends response period to 31/1/2023

14

Monday, 9 January 2023

SARA Response: Extends response period to 28/2/2023

Wednesday, 18 January 2023

Applicant Requests extension on Information Response to 28/2/2023

16

Wednesday, 15 February 2023

Applicant Lodged A Change to the Application [17 to 18 lots]

18

Wednesday, 15 February 2023

FCRC Refers Change application to SARA

19

Tuesday, 28 February 2023

Applicant Requests extension on Information Response to 28/4/2023

21

Tuesday, 28 February 2023

FCRC Extension Agreement to 28/4/2023

20

Monday, 17 April 2023

Applicant Requests extension on Information Response to 31/5/2023

22

Tuesday, 16 May 2023

FCRC Extension Agreement to 31/5/23

23

Wednesday, 28 June 2023

Applicant Requests extension on Information Response to 30/7/2023

25

Wednesday, 28 June 2023

FCRC Extension Agreement to 31/7/23

24

Monday, 24 July 2023

Applicant Requests extension on Information Response - 3 months

28

Monday, 24 July 2023

SARA Response: Extends response period to 30/10/2023

27

Monday, 24 July 2023

FCRC Extension Agreement to 31/7/23

26

Thursday, 12 October 2023

FCRC Extension Agreement to 31/1/2024

29

Thursday, 12 October 2023

Email (mydas-notifications-prod2@qld.gov.au) No attachment (SARA?)

30

Tuesday, 30 January 2024

FCRC Extension Agreement to 28/2/2024

31

Monday, 19 February 2024

Applicant Requests extension on Information Response - 90 Business days

32

Monday, 19 February 2024

FCRC Extension Agreement to 8/7/2024

33

Monday, 19 February 2024

SARA Response: Extends response period to 9/7/2024

34

Thursday, 7 March 2024

Project Manager Meets with FCRC

Thursday, 20 June 2024

The Applicants consultant planner, responded to the SIR and CIR by providing material to FCRC - with a copy to SARA.

The material provided, included:

·         A report from Stormwater Consulting, specialist in stormwater engineering, including hydrology and hydraulic. (SCR24)

·         Advice from International Coastal Management, specialists in coastal engineering (ICM24)

·         Supporting Planning Report from consultant planner Urban Planet (PR24A)]

35

Thursday, 20 June 2024

Information Request Stage - Ends

Thursday, 20 June 2024

Decision Stage  - Starts

Tuesday, 9 July 2024

SARA raise an issue, in an Advice Notice, regarding Operational Works, identified in SCR24, related to a stormwater drainage design located within the forestry reserve.

36

Tuesday, 9 July 2024

SARA Advises FCRC Applicant agrees to extend Referral Period to 26/7/2024

37

Tuesday, 23 July 2024

SARA Advises FCRC Applicant agrees to extend Referral Period to 21/10/2024

38

Tuesday, 3 September 2024

Applicant submits changes to DA21 (DA24)

The material provided, included:

·         A report from the Appellant's consultant planner Urban Planet (PR24B) demonstrating the matter relevant to the Advice Notice, was now redundant.

·         Amended layout plan reducing the lot yield from 18 down to 5

40

Monday, 9 September 2024

FCRC advised SARA of Amended Application

39

Tuesday, 17 September 2024

Project Manager contact SARA-Re delays

Tuesday, 24 September 2024

SARA responds - Request more storm water information

Tuesday, 24 September 2024

Project Manager responds - Providing Information

Sunday, 29 September 2024

Project Manager contact SARA-Re Response to Information

Tuesday, 1 October 2024

Project Manager contact SARA-Re change of officers

Thursday, 3 October 2024

SARA Responds-Seeking response to Advice Notice (SAN24)

Friday, 4 October 2024

Project Manager responds -Re confusion.

Tuesday, 8 October 2024

SARA Responds to consultant planner - Re High Impact Earthworks

Thursday, 10 October 2024

Project Manager responds- SARA Refuses to negotiate with Project Manager.

Monday, 14 October 2024

SARA responds with Draft - deleting conditions 2, 7 and 9

Tuesday, 15 October 2024

Appellant makes 3rd representation to SARA

Thursday, 17 October 2024

SARA issues Referral Agency Response to assessment manager (RAR1)

41

Friday, 18 October 2024

SARA responds. - Deleting conditions 2, 7, reinstate condition 9

Monday, 21 October 2024

SARA issues amended Referral Agency Response to assessment manager. (RAR2)

Wednesday, 23 October 2024

Applicant makes 1st representation to SARA

42 and 43

Wednesday, 30 October 2024

SARA responds. -Seeking further information

Thursday, 31 October 2024

Applicant makes Representation No2 to SARA

Thursday, 31 October 2024

Applicant makes 2nd representation to SARA

Wednesday, 13 November 2024

SARA Draft - Changed to Conditions

Thursday, 14 November 2024

Applicant responds to Draft

Thursday, 21 November 2024

SARA provides amended advice to FCRC

45

Thursday, 21 November 2024

FCRC Extension Agreement [Decision period] to 10 business days

44

Monday, 2 December 2024

Project Manager seeks advice re issue of Decision Notice-FCRC responds advising it is due on 6 December 2025

Wednesday, 4 December 2024

FCRC Extends decision period to 13 December 2024

46

Monday, 6 January 2025

Project Manager seeks advice re issue of Decision Notice extended to the 13 December 2025 - FCRC responds decision notice to be issued that week

Friday, 10 January 2025

FCRC sent draft of Recommended Condition

Monday, 13 January 2025

Project Manager responds raising issues.

Wednesday, 15 January 2025

Project Manager submits Submission; - Request advice.

Tuesday, 28 January 2025

Project Manager seeks update - FCRC responds – will chase up! 

Wednesday, 29 January 2025

Project Manager provides draft of acceptable conditions

Monday, 3 February 2025

Project Manager seek update on Decision Notice

Wednesday, 5 February 2025

Project Manager seek update- FCRC responds Decision Notice to be issued 13 February 2025

Wednesday, 12 February 2025

Project Manager seek meeting - Meeting arranged for 18 February 2025

Monday, 17 February 2025

Project Manager submits material relevant to meeting discussions - FCRC Responds - Executive Manager advising that there is no area for negotiation on the issues raised-

Proposes cancelling meeting –

Project Manager accepts that suggestion but advises that this will result in the matter ending up in court. 

Friday, 21 February 2025

FCRC issued Decision Notice (DN25) and Infrastructure Charges Notice number 5138178 (ICN25)

48

Friday, 21 February 2025

Decision Stage - Ends

Friday, 21 February 2025

Appeal Process   - Starts

Wednesday, 19 March 2025

Applicant files Notice of Appeal IN P&E Court

50

Thursday, 20 March 2025

Applicant Suspends Appeal Period ICN

49