Conditions

SARA

·      No 1

·      No 2

·      No 3

FCRC

Acronyms

Conditions Commentary

 

Condition 1

The Process

Putting aside for the moment, the issue of copyright and the authority to amend documents that are copyright protected by another party, where does SARA draw its legislative authority, as part of the assessment process, to draft/modify information that is contained within the common material of an applicants development application, without approval of the applicant?

Nor is there a clear logical explanation for the necessity to detail the materials, within a plan provided by the applicant.

Also putting aside for the moment, the amendment activity carried out by SARA to generate new content in the common materials, the most important question to be answered is:

Q1 Was the amendment of the Site Layout plan, necessary in order for DA21 to achieve the objectives of an assessment benchmark?

The Queensland government already has provided mapping in relation to DA21.

The content and context of the material drafted by SARA onto the plan and legislation to achieve the objective the purpose of the detailed information, documented on the plan, already existed.

Further a planning report, (PR) by the planning consultant, which comprises a component of the common material of DA21, was provided to SARA. The PR, detailed the areas and the circumstances, that were the focus of the material, drafted by SARA.

If SARA felt the need to reinforce this position, this could just as easy have been achieved by the use of text within a condition, if such was felt necessary to ensure the development achieved the objectives of the assessment benchmarks.

The Content

Condition No1 makes particular reference to the material inserted into an amended document (development layout plan) (DLP) by SARA on 17 October 2024 and 21 November 2024.

There are 3 issues:

Item 1 The text placed on the DLP reads:

Areas shaded in blue represents the Wetland Protection Area 50m buffer and…”

The first matter of contention is the wording. The area shaded in blue does not represent the 50m buffer it represents the portion of the 50m buffer relevant to DA21 (15m)

Item 2

When read in conjunction with Condition 9a the significance of the drafting becomes more obvious because 9a requires the development to Provide a 50m wide buffer for the purposes of.

This matter was brought to SARA attention but they declined to redraft the condition

On 30 October 2024 SARA advised by email

"- the blue area within Proposed Lot 5 on the SARA approved plan indicates the 50-metre buffer from the mapped High Ecological Significance (HES) wetland (distance of this buffer is based on the subject site being located within the Low-Density Residential Zone under the Fraser Coast Planning Scheme 2014"

Yet the wording in the condition remained unchanged to provide the essential clarity and preciseness, required for a development condition.

Item 3 The text placed on the DLP reads:

“…and is to remain development free for the purposes of protecting the wetland environmental values.

This Condition requires that this defined area must remain development free.

When read in conjunction with Condition 9b the significance of the drafting becomes more obvious because 9b requires the development to Provide buffer elements in the locations shown on..

One has to assume that the buffer elements referred to, are to be placed within the wetland buffer area, defined on the site plan in blue.

However, there is no information as to:

(a)    what might constitute a buffer element? or

(b)   what buffer elements are considered required? or

(c)    why the addition of buffer elements are considered required? or

(d)   any consideration as to how one might place a buffer element, (the doing of which would constitute a development under PA16), in an area where development has been prohibited by this Condition.

Further, on 20 June 2024 the applicant's planning consultant, responded to Information Request by SARA on the 7 January 2022, by providing a copy of the material, also provided to the assessment manager, on that date.

The material provided, included a report from a firm of consulting engineers Stormwater Consulting, specialists in the hydrology and hydraulic of stormwater.

The 52-page report addressed all the issues associated with both:

(a)    overland flow from the adjoining areas above the contour level for the subject site (including the wetlands); and

(b)   the stormwater that would fall upon the development.

The findings of the report were that while the property is affected by overland flow from a catchment to the west, the flows coming from west of the site, passing through the site and discharges in the north-eastern site corner.[1] Map

That is, all overland flow comes from uphill of the site where the wetland is located and *in the absence of any modification of the development, to reverse that flow, there is no possibility that storm water from the development can ever have any influence at all, on the wetland's water quality.

And confirmed this within the report, by advising that:

The proposed development would comply with PO3, PO4 and PO5 of State Code 9 [2]

*No modification of the site, that would change that circumstance, is present in the current DA21.

Then, on 9 July 2024 SARA raise the issue of Operational Works set out in the consultants report for a proposed Berm within the wetlands protection area and called for detailed plans of proposed earthworks in the buffer zone to demonstrate compliance with PO3 of State Code 9.

No other comment/request was made in relation to the material submitted on 20 June 2024.

On 3 September 2024 the applicant amended DA21 and provided a copy to SARA. The amendment removed the proposal to utilise part of the wetlands protection area requiring a Berm to divert overland flow, thus making the matter raised in the Agency's advice notice of 9 July 2024 redundant.

Then on 17 September 2024 the applicant contacted SARA seeking to confirm that SARA was now in possession of all the material necessary to issue their Advice Notice to the assessment manager.

However, again SARA responded on 24 September 2024 with a request to provide more detailed stormwater management information. The applicant responded to that request on that same day, drawing to SARA attention that they were already in possession of stormwater management details sufficient to satisfy their enquiry.

On 17 October 2024 SARA provided their Advice Notice to the assessment manager.

On 22 October 2024 the applicant responded to SARAs advice to the assessment manager, requesting a review of their conditions including No I and No 3.

In that response, the applicant brought to the attention of SARA, the existence of a document published by the Department Environment and Science in 2022 (Guidelines) that clearly provided advice, (PO1) in relation to wetland buffers to the effect that:

Whilst development is intended to be located outside the buffer, it is possible for low-impact elements of the development proposal to be located within the buffer…”

Under the above cited Guidelines there is provision:

(a)    for the placement of accepted developments within wetland protection areas as well as the facility-

(b)   to make application to amend mapping in relation to these protection areas.

Condition No 1 as proposed would preclude any of these opportunities for any development to occur in the defined area - even if it could be delivered in accordance with the requirements of legislation, guidelines or assessment benchmarks. Or in fact as currently required by this condition.

Plus, there is no facility under the PA16 to amend a development permit condition in the future, once a development is complete. Thus, permanently denying any of the above accorded facilities.

Item 4 The text placed on the DLP reads:

Area shaded in red represents the Erosion Prone Area and is to remain develpment free for the purposes of coastal protection.

As detailed in Item 3 above SARA had in their possession since 20 June 2024, advice from a specialist in coastal engineering, that there were options available for dealing with sites within the erosion prone zone. Filling the land to a certain level was only one of the options.

In the third submission to SARA (20 October 2024) regarding this conditions it was requested that the existence of the options be included within the condition. This request was denied.

Item 5 The text placed on the DLP reads:

Amended in red bySARA to maintain development free buffers in the Erosion Prone Area and wetland Protection Area and to ensure proposed Lots 1 and 2 are developed outside the Erosion Prone Area.

The drafting is confusing, because under Condition 9(a) the development is required to Provide (and maintain) a 50m wide buffer for the purposes of.and under 9(b) to provide development within this Wetland Protection Area.

13 November 2024 -SARA provided a Draft of changed condition

15 November 2024 -The applicant responded to the Draft

21 November 2024 -SARA provided the assessment manager with their final advice. Some proposed changed set out in SARA'a Draft were then abondoned by SARA.

For all the above reasons Condition No1 is an unreasonable imposition on the development and not reasonably required to ensure the developments achieve the overarching requirements of a planning instrument.

…………………..

Condition 3

Condition No 3 is technically a replication of some of the content and context provided for on the amended Site Plan, the subject of Condition No1 - dealing as it does with the erosion prone area circumstance.

On 21 December 2021, SARA as referral (concurrence) agency was provided with a copy of the development application and the common material for the DA21.

The common material included planning report (PR) from the applicant's consultant planner.

That PR advised, in relation to state mapping, the existence of the erosion prone areas within the subject site and on advice of the consultant planner, the site was not subject to coastal processes but further indicated that a section was effected by erosion prone areas mapping and that, the site will be required to be filled to levels specified by the assessment manager.

This would provide future security for persons and property as a consequence of the development.

The PR also advised that in accordance with Performance Outcome PO2 of State Code 8, that this filling of the site was to be addressed by a future development application (*Operational work) that would accommodate delivery of the required performance outcome.

*The Planning Regulation 2017 in Schedule 10 Part 17 provides for assessment and referrals for Operational work in coastal management district.

On 25 January 2022 Fraser Coast Regional Council (Council) issued a Flood Search Report (FSR) for the subject site. The FSR indicated the Property was within the Storm-Tide Hazard area and provided a Defined Storm-Tide Level value of RL 2.4m AHD for the development.

Council's planning scheme required that land within a development, within a Storm-Tide Hazard Area was required:

·         to be filled to that level; and

·         to the standard and the process- defined within Council's development policies.

The development type for the filling of land, is Operational Works.

On 7 January 2022 SARA issued an information request, the material in that request indicated their knowledge that a portion of the site was expected to be inundated by sea level rise by the year 2100 and the heights of the sea was determined to be 800mm above the present-day sea level.

Funnily enough though the information request also advised that No information had been provided to demonstrate how this coastal hazard would be mitigated for the subject site. This, despite being in possession of the PR which had already flagged this issue and prescribed a compliance solution.

On 20 June 2024 the applicant's planning consultant responded to the information request by providing a copy of the material provided to the assessment manager on that date.

The material provided included advice from a firm of consulting engineers, International Coastal Management, specialists in coastal engineering developments.

The advice identified the exact AHD that would represent the 2100 sea level rise for that particular parcel of land (RL 2.33 AHD) and advice as to options that were available to meet current requirements to protect land in the development from prescribed, future inundation sea levels.

On 17 October 2022 SARA provided its Referral Advice to the assessment manager. That advice contained the conditions that were to be attached to any development approval for the application. That advice included Condition No3

On 22 October 2024 the applicant responded to that advice to the assessment manager requesting a review of the conditions and requested the condition be redrafted to reflect the options provided for by the specialist consultant coastal engineer.

On 11 November 2024 the agency provided a draft amendment to the conditions. The draft did not include changes to Condition 3

The two lots (Lot1 and Lot2) identified in the Condition1 and Condition 3, contained land that is below the AHD set under Councils requirements in the FSR.

The assessment benchmarks under Councils planning scheme, for a RAL requires lot filling for land in Storm-Tide Hazard area to RL 2.40 AHD. That is higher than the RL AHD required for the 2100 sea level rise.

Thus, the requirements under the planning scheme are in excess of those required by State Code 8.

Further and more importantly the requirement of Condition 3 is already mandatory under Condition 1. Reproduced as Condition 3 appears as nothing more than a reminder to comply with the lawful requirement of Condition 1.

While the retention of SARAs Conditions 3 could be tolerated as simply a frustration of the conduct of bureaucracy, if it did not produce an unacceptable circumstance. But Section 259 of PA16 makes it an offence not to comply with a development condition. The retention of Condition 3 creates the opportunity for a double jeopardy style outcome for a single event. [Breach of condition 1 and 3] Plus a development condition run with the land title and can never be changed.

For this very reason Condition 3 is unreasonable and should be deleted, even if Condition 1 is retained.

................................

Condition 4

This condition refers to the standard of a product, for the material used as part of the performance of 'work', required by Condition 3, to be carried out under the authority of a development permit for Operational Works.

Putting aside for one moment the above in relation to Operational Works, the condition refers to a term clean material and defines that term as being a material free from prescribed water contaminants.

No reference is made to the assessment benchmark requiring this to be considered as part of the Code assessment process for DA21 or reference to documents called up by an assessment benchmark that could provide scope and quantitative values for materials that are prescribed as water contaminants, to be avoided in fill material, within residential development.

As well as that anomaly, DA21 for referral is one of reconfiguring of a lot (RAL), and not operational works, that will be required to be carried out under a seperate developmnt approval, in order for this development be completed.

*The Planning Regulation 2017 in Schedule 10 Part 17 provides for assessment and referrals for Operational work in coastal management district.

Further, under the provisioning of titling legislation in Queensland, local governments are required to approve the plan of subdivision for RAL.

If there is other associated development work, outside the RAL, that is required to be completed, local governments will not atthorise the documentation, necessary for lodgement to the titles office, until all development are finished in accordance with their approval conditions.

The activity described in Condition 4 does not form part of DA21. It will however invariably form part of the performance of work under any future Operational Work development application

Therefore Condition 4 is not relevant to the DA21 and should be removed.

................................

Condition 5

This condition presents the same circumstances as outlined above, in Condition 4, and accordingly therefore Condition 5 is not relevant either, to the DA21 and should be removed.

................................

Condition 6

This condition is an exact copy of Condition 1. There is no reasonable requirement for it to be replicated.

When referral agencies act as an assessing authority for a development, often there will be a number of assessments benchmarks they are required to assess against. There is no requirement in the assessment process to replicate a condition that delivers the same compliance outcome applicable to multiple assessments benchmarks.

..................................

Condition 8

This condition presents the same circumstances as outlined above, about Condition 4 and accordingly therefore Condition 5 is not relevant to DA21 and should be removed.

..................................

Condition 9(a)

This condition replicates the objectives defined in Condition 1 and Condition 3 and serve no purpose in ensuring the development meets the objectives set within the provisions of PA16.

..................................

Condition 9(b)

There are a number of elements to this condition

Firstly, on the surface, this condition appears to be building upon the conditions outlined in Condition 1 and Conditions 3 by now requiring that the provision of buffer elements in locations shown on the amended plan and offers an explanation for the condition as, to assure the development achieves the purposes set out in the Queensland Wetland Buffer Planning Guideline 2011.

The assessment benchmark State Code 9, in the section Using This Code provides advice that this code includes a glossary of terms for definitions in the code and reference documents including the guideline State Development Assessment Provisions State Code 9: Great Barrier Reef wetland protection areas (SC9 Guidelines)

Firstly, Guidelines are not statutory assessment benchmarks. Guidelines are provided to help clarify requirements or provide general, not mandatory, advice. The Guideline reinforce this position on Page 4 -This guideline is not a statutory document.

It would appear that the Queensland Wetland Buffer Planning Guideline 2011 (QWBP Guidelines) cited in Condition 9(b) are called up via the SC9 Guideline

Part 4.0 Information requirements

This Part of SC9 Guidelines states:

If proposing a reduced buffer or wetland area, an ecological values assessment demonstrating compliance with the Queensland Wetland Buffer Planning Guideline. and provides a hyperlink to a copy of the QWBP Guidelines.

Nowhere in DA21, is it proposed to develop a wetland area, nor is the development seeking a reduced buffer, for which guidance may then needto be referrence from the QWBP Guidelines.

Next, nowhere in the QWPB Guideline is there information that clearly identified the purpose” of the Guidelines. However, using Section 2 of QWPB Guideline headed Purpose and scope, a purpose can be extrapolated/deduced from within the opening paragraph.

The QWPB Guideline primarily functions to support a Buffer Design Method which is intended to evolve from fundamental concepts and using a systematic approach in the design.

Its purpose, it would seem, is to assist those involved with wetland development planning by providing a series of steps and considerations associated with designing a wetland and also provide some support to those involved in the management of wetlands though it is not abundantly clear in what form that support takes, other than guidance information in the document.

Then of particular interest to DA21, the documents states

This guideline cannot override legislative requirements however it can inform decisions required under Queensland legislation to the degree that legislation allows for guideline consideration

And then the statement in the QWPB Guideline:

Wetland buffers also need to be distinguished from wetland trigger areas under legislation. Trigger areas are those areas which trigger an assessment of the impacts for a development the resulting buffer may be significantly narrower than the trigger area depending on the nature of the development

The QWPB Guideline is not an CODE assessment benchmark; as it clearly is IMPACT based and requires the application of a'personal opions' and nor is it called up in an assessment benchmark - relevant to DA21.

Keep this in mind when we come to the consideration of compliance with the legislation in undertaking a code assessment of a development application.

..................................

Condition 9(c)

Places a requirement on the production, by an undefined but appropriately qualified person, of documentation, that it is assumed, would contain evidence of, what is termed:

·         The 50 m wide buffer as identified in Conditions 1; 6; and 9(a) are still in existence; and

·         The provision of undefined buffer elements in undefined locations, has occurred,

at some stage, prior to when the local government, in accordance with the requirements of the subdivision of land titling, issues their approval to the titles office to approve the plan of subdivision documentation.

One has to asume that if this condition remains in place, the condition would expire on compliance with 9(c) (On sealing of the survey plan) and one would have to do ask the question,

In what way does this ensure ongoing maintenance of the buffer area, into the future, and ensure the compliance with the purposes set out in the document called up by Condition 9".

Lot 5 of the proposed DA21, which is the subject of the prohibitions placed by Conditions 1 and 6, has ample space to accommodate future development, in accordance with both the zoning and the planning scheme assessment benchmarks.

The inclusion of conditions to prohibit future development in the areas identified on the Site Plan. No matter how much the development can be supported would, because of the lawful nature of development conditions, be a permanent block to any further development considerations, even if such developments were to demonstrate that future development in those area can be accommodated within both legislative and guideline documentation.

For these reasons Condition 9 is unreasonable and should be deleted.